    Metrics
Height 203.7 m / 668 ft
Floors 51
Official Name
The current legal building name.

8 Bishopsgate

Other Names
Other names the building has commonly been known as, including former names, common informal names, local names, etc.

Prussian Blue, 6-8 Bishopsgate, 150 Leadenhall Street

Type
CTBUH collects data on two major types of tall structures: 'Buildings' and 'Telecommunications / Observation Towers.' A 'Building' is a structure where at least 50% of the height is occupied by usable floor area. A 'Telecommunications / Observation Tower' is a structure where less than 50% of the structure's height is occupied by usable floor area. Only 'Buildings' are eligible for the CTBUH 'Tallest Buildings' lists.

Building

Status
Completed
Architecturally Topped Out
Structurally Topped Out
Under Construction
Proposed
On Hold
Never Completed
Vision
Competition Entry
Canceled
Proposed Renovation
Under Renovation
Renovated
Under Demolition
Demolished

Completed

Completion

2023

Country
The CTBUH follows the United Nations's definition of Country, and thus uses the lists and codes established by that organization.

United Kingdom

City
The CTBUH follows the United Nations's definition of City, and thus uses the lists and codes established by that organization.

London

Address

8 Bishopsgate

Function
A single-function tall building is defined as one where 85% or more of its usable floor area is dedicated to a single usage. Thus a building with 90% office floor area would be said to be an "office" building, irrespective of other minor functions it may also contain.

A mixed-use tall building contains two or more functions (or uses), where each of the functions occupy a significant proportion of the tower's total space. Support areas such as car parks and mechanical plant space do not constitute mixed-use functions. Functions are denoted on CTBUH "Tallest Building" lists in descending order, e.g., "hotel/office" indicates hotel function above office function.

Office

Structural Material
All-Steel
Both the main vertical/lateral structural elements and the floor spanning systems are constructed from steel. Note that a building of steel construction with a floor system of concrete planks or concrete slab on top of steel beams is still considered an “all-steel” structure as the concrete elements are not acting as the primary structure.

All-Concrete
Both the main vertical/lateral structural elements and the floor spanning systems are constructed from concrete which has been cast in place and utilizes steel reinforcement bars and/or steel reinforced concrete which has been precast as individual components and assembled together on-site.

All-Timber
Both the main vertical/lateral structural elements and the floor spanning systems are constructed from timber. An all-timber structure may include the use of localized non-timber connections between timber elements. Note that a building of timber construction with a floor system of concrete planks or concrete slab on top of timber beams is still considered an “all-timber” structure as the concrete elements are not acting as the primary structure.

Mixed-Structure
Utilizes distinct systems (e.g. all-steel, all-concrete, all-timber), one on top of the other. For example, a Steel Over Concrete indicates an all-steel structural system located on top of an all-concrete structural system, with the opposite true of Concrete Over Steel.

Composite
A combination of materials (e.g. steel, concrete, timber) are used together in the main structural elements. Examples include buildings which utilize: steel columns with a floor system of reinforced concrete beams; a steel frame system with a concrete core; concrete-encased steel columns; concrete-filled steel tubes; etc. Where known, the CTBUH database breaks out the materials used within a composite building’s primary structural elements.

Concrete-Steel Composite

Energy Label

BREEAM Outstanding, EPC A

Height
Architectural
Height is measured from the level of the lowest, significant, open-air, pedestrian entrance to the architectural top of the building, including spires, but not including antennae, signage, flag poles or other functional-technical equipment. This measurement is the most widely utilized and is employed to define the Council on Tall Buildings and Urban Habitat (CTBUH) rankings of the "World's Tallest Buildings."

203.7 m / 668 ft

To Tip
Height is measured from the level of the lowest, significant, open-air, pedestrian entrance to the highest point of the building, irrespective of material or function of the highest element (i.e., including antennae, flagpoles, signage and other functional-technical equipment).
203.7 m / 668 ft
Occupied
Height is measured from the level of the lowest, significant, open-air, pedestrian entrance to the highest occupied floor within the building.
194.3 m / 637 ft
Floors Above Ground
The number of floors above ground should include the ground floor level and be the number of main floors above ground, including any significant mezzanine floors and major mechanical plant floors. Mechanical mezzanines should not be included if they have a significantly smaller floor area than the major floors below. Similarly, mechanical penthouses or plant rooms protruding above the general roof area should not be counted. Note: CTBUH floor counts may differ from published accounts, as it is common in some regions of the world for certain floor levels not to be included (e.g., the level 4, 14, 24, etc. in Hong Kong).

51

Floors Below Ground
The number of floors below ground should include all major floors located below the ground floor level.

3

# of Elevators
Number of Elevators refers to the total number of elevator cars (not shafts) contained within a particular building (including public, private and freight elevators).

21

Top Elevator Speed
Top Elevator Speed refers to the top speed capable of being achieved by an elevator within a particular building, measured in meters per second.

8 m/s

Tower GFA
Tower GFA refers to the total gross floor area within the tower footprint, not including adjoining podiums, connected buildings or other towers within the development.

87,355 m² / 940,281 ft²

Rankings

#
2021
Tallest in the World
#
66
Tallest in Europe
#
11
Tallest in United Kingdom
#
11
Tallest in London

Construction Schedule

2015

Proposed

2019

Construction Start

2023

Completed

Developer
Architect
Design

Usually involved in the front end design, with a "typical" condition being that of a leadership role through either Schematic Design or Design Development, and then a monitoring role through the CD and CA phases.

Structural Engineer
Design

The Design Engineer is usually involved in the front end design, typically taking the leadership role in the Schematic Design and Design Development, and then a monitoring role through the CD and CA phases.

MEP Engineer
Design

The Design Engineer is usually involved in the front end design, typically taking the leadership role in the Schematic Design and Design Development, and then a monitoring role through the CD and CA phases.

Project Manager

The CTBUH lists a project manager when a specific firm has been commissioned to oversee this aspect of a tall building’s design/construction. When the project management efforts are handled by the developer, main contract, or architect, this field will be omitted.

Contractor
Main Contractor

The main contractor is the supervisory contractor of all construction work on a project, management of sub-contractors and vendors, etc. May be referred to as "Construction Manager," however, for consistency CTBUH uses the term "Main Contractor" exclusively.

Other Consultant

Other Consultant refers to other organizations which provided significant consultation services for a building project (e.g. wind consultants, environmental consultants, fire and life safety consultants, etc).

Façade

These are firms that consult on the design of a building's façade. May often be referred to as "Cladding," "Envelope," "Exterior Wall," or "Curtain Wall" Consultant, however, for consistency CTBUH uses the term "Façade Consultant" exclusively.

Quantity Surveyor
Sustainability
Wind
Material Supplier

Material Supplier refers to organizations which supplied significant systems/materials for a building project (e.g. elevator suppliers, facade suppliers, etc).

Fire Stopping
Owner
Mitsubishi Estate Company, Ltd
Developer
Mitsubishi Estate Company, Ltd; Stanhope
Architect
Design

Usually involved in the front end design, with a "typical" condition being that of a leadership role through either Schematic Design or Design Development, and then a monitoring role through the CD and CA phases.

Structural Engineer
Design

The Design Engineer is usually involved in the front end design, typically taking the leadership role in the Schematic Design and Design Development, and then a monitoring role through the CD and CA phases.

MEP Engineer
Design

The Design Engineer is usually involved in the front end design, typically taking the leadership role in the Schematic Design and Design Development, and then a monitoring role through the CD and CA phases.

Project Manager

The CTBUH lists a project manager when a specific firm has been commissioned to oversee this aspect of a tall building’s design/construction. When the project management efforts are handled by the developer, main contract, or architect, this field will be omitted.

Contractor
Main Contractor

The main contractor is the supervisory contractor of all construction work on a project, management of sub-contractors and vendors, etc. May be referred to as "Construction Manager," however, for consistency CTBUH uses the term "Main Contractor" exclusively.

Other Consultant

Other Consultant refers to other organizations which provided significant consultation services for a building project (e.g. wind consultants, environmental consultants, fire and life safety consultants, etc).

Façade

These are firms that consult on the design of a building's façade. May often be referred to as "Cladding," "Envelope," "Exterior Wall," or "Curtain Wall" Consultant, however, for consistency CTBUH uses the term "Façade Consultant" exclusively.

Planning
Gerald Eve
Quantity Surveyor
Sustainability
Wind
Material Supplier

Material Supplier refers to organizations which supplied significant systems/materials for a building project (e.g. elevator suppliers, facade suppliers, etc).

Fire Stopping

CTBUH Awards & Distinctions

Best Tall Building, by Region, Europe 2024 Award of Excellence

2024 CTBUH Awards

Best Tall Building, by Height, 200-299 meters 2024 Winner

2024 CTBUH Awards

 

Videos

30 October 2017 | London

Interview: Chris Wilkinson

Chris Wilkinson of Wilkinson Eyre Architects is interviewed by Chris Bentley during the 2017 CTBUH Australia Conference.

Research

17 October 2016

Exploring Geometry and Form in Tall Buildings

Chris Wilkinson, Wilkinson Eyre Architects

Using four tower designs on four continents – the Guangzhou International Finance Center in China, the Crown Sydney Resort Hotel in Australia, 45 Bay Street...

 

About 8 Bishopsgate

This design stands out among its neighbors with its visually light and elegant design, emphasizing sustainability and occupant well-being. Breaking the traditional tower massing into smaller blocks, the building achieves generous roof terraces, and integrates seamlessly with its surroundings while prioritizing human scale and environmental consciousness. Dedicated amenity spaces are open to tenants and the public, including a 50th floor viewing gallery.

CTBUH Awards & Distinctions

Best Tall Building, by Region, Europe 2024 Award of Excellence

2024 CTBUH Awards

Best Tall Building, by Height, 200-299 meters 2024 Winner

2024 CTBUH Awards

30 October 2017 | London

Interview: Chris Wilkinson

Chris Wilkinson of Wilkinson Eyre Architects is interviewed by Chris Bentley during the 2017 CTBUH Australia Conference.

19 October 2016 | London

Exploring Geometry and Form in Tall Buildings

Wednesday, October 19, 2016. Guangzhou, China. Chris Wilkinson of Wilkinson Eyre, presents at the 2016 China Conference Plenary 5: "Beyond Guangzhou: Other Settings" Using four...